After putting tasks in the correct sequence for a project schedule, what is the next step?

Master the Project Management Foundations Exam with interactive quizzes and comprehensive study guides. Enhance your skills, and gain confidence with detailed explanations and practice questions. Achieve certification effortlessly!

After sequencing tasks in a project schedule, the logical next step is to add the time estimated for each task. This process is known as estimating durations, and it is critical for understanding how long the entire project will take to complete. By assigning time estimates, the project manager can develop a more realistic timeline and forecast when the project will meet its deliverables.

Estimating task durations allows the project manager to identify potential bottlenecks and plan accordingly. It creates a foundation upon which further planning and analysis can be performed, such as establishing milestones and determining the overall project timeline.

Resource allocation comes into play later in the project management process, as it involves assigning the necessary resources to tasks in consideration of their durations. While a dependency diagram is useful for visualizing task relationships, creating one would typically occur during the planning phase, and while risks should be updated throughout the project lifecycle, this step doesn't directly tie to task sequencing and duration estimation. Therefore, adding time estimates to each task is a basic yet crucial step that directly follows task sequencing in project management.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy