After saving the project baseline, project documents will be under the control of what process?

Master the Project Management Foundations Exam with interactive quizzes and comprehensive study guides. Enhance your skills, and gain confidence with detailed explanations and practice questions. Achieve certification effortlessly!

The correct answer is that after the project baseline is established and saved, project documents fall under the control of the change management process. This is because the baseline serves as a reference point for the project's scope, schedule, and costs. Once these baselines are set, any changes to the project must be systematically managed to ensure that the project remains aligned with its goals and objectives.

The change management process is crucial in monitoring and controlling changes or modifications to the project's scope, schedule, or cost. It helps to assess the impact of any proposed changes, ensures proper documentation, and facilitates communication among stakeholders regarding any adjustments being made. This process ensures that all alterations are justified, properly approved, and documented, thereby maintaining the integrity of the project.

While the other processes mentioned, such as quality management, resource management, and risk management, play important roles in overall project execution, they do not specifically control the changes to the project baseline documents. Quality management is focused on ensuring the project's deliverables meet specified standards, resource management deals with the efficient and effective deployment of people and materials, and risk management involves identifying, assessing, and mitigating potential project risks. Though all these aspects are interconnected, it is change management that directly oversees adjustments to the project baseline documentation.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy